Inspection of the EFC document of DOP, mid term review report and table in deans mail uncover that; the projects from where money is siphoned off or diverted those are care fully avoided/omitted for presentation
Rs. FIVE CRORES AND SIXTY LACS Sanctioned by Planning Commission GOI for three well defined 11th Five year plan projects vanished after reaching NIPER Mohali.
PI (who conceptualized) of those projects has no idea about the money received.
What happened to the money? "Albert Pinto Ko Gussa Esi Liay Aata Hai".
Don't ask who is Albert Pinto, read on till the end..................... Khud Jaan Jao
---------------------------------------------------------------------------------------------
----------------------------------------------------------------------------------------------------------------------------------
Detailed chronological account of fund diversion
Rs. FIVE CRORES AND SIXTY LACS Sanctioned by Planning Commission GOI for three well defined 11th Five year plan projects vanished after reaching NIPER Mohali.
PI (who conceptualized) of those projects has no idea about the money received.
What happened to the money? "Albert Pinto Ko Gussa Esi Liay Aata Hai".
Don't ask who is Albert Pinto, read on till the end..................... Khud Jaan Jao
---------------------------------------------------------------------------------------------
From: Dr. Anand Sharma xxx@niper.ac.in
Sent: Wednesday, June 23, 2010 10:17 AM
To: 'ucbanerjee@niper.ac.in'; 'rkartha@niper.ac.in'
Subject: 11th Five Year Plan
Sent: Wednesday, June 23, 2010 10:17 AM
To: 'ucbanerjee@niper.ac.in'; 'rkartha@niper.ac.in'
Subject: 11th Five Year Plan
Sir
Please find the budget proposal for R&D specialization in
Department o Pharmaceutical Management.
Regards
Dr. Anand Sharma
Responsibility Center Dated 17
.6 . 2010
11th Five Year Plan Schemes, 2007-2012
Information for the year 2010-2011
1.
Scheme
Number: [ N – 14 ] Research
and Development specialization in Management
2.
Proposed
work under the Scheme: for the
period of 1.04.2010 to 31.03.2011:
i)
Induction of Faculty and
ii)
Development of Course content and teaching
material
3.
Expected
deliverables:
i)
Initiation of Research and Development
specialization in Management
ii)
Induction of two new Faculty
iii)
Development of Course content and teaching
material
iv)
Training of students in new specialization (60)
4.
Budget: Total Requirement : 13.2 + 5+ 5 + 6= 29.2 lakhs
i) Total fund allocated for the Scheme: 1.6 Crore
ii) Money spent so far on the Scheme (2007-2010): Not Known
i) Total fund allocated for the Scheme: 1.6 Crore
ii) Money spent so far on the Scheme (2007-2010): Not Known
iii) Fund
to be spent during the financial year, 2010 - 11:
a) Salary
of Minimum two Faculty Positions
as per norms
( apprx. Rs. 55000/- pm , total budget Rs.
13.20 lakhs.)
b) Misc.
Expences : Travel course material/ books/journals etc. – 5 lakh.
c) Furnishing
of reading of reading rooms – 6 lakhs
5.
Equipments
to be purchased: Furnishing of two Faculty rooms – Rs. 5 lakh each
(Furniture/table/chairs/cabinets/A/C, Computers etc.
6.
Man power
requirement : Two Faculty positions
7.
Hurdles/remarks (if any) :
Sd/-
Dr. Anand Sharma
----------------------------------------------------------------------------------------------------------------------------------
ADVANCE COPY. THROUGH PROPER CHANNEL FOLLOWS
Parikshit Bansal, Ph.D. (Biochemistry), LLB
In-Charge, IPR Cell
National Institute of Pharmaceutical Education and Research
(NIPER), Mohali-160067 (Punjab)
Email-pbansal@niper.ac.in
Dated: 18.07.2011
Dr V. M. Katoch
Chairman, Board of
Governors, NIPER
Secretary to Govt. of
India, Department of Health Research &
Director General,
Indian Council of Medial Research
Ramalingaswami
Bhawan,
Ansari Nagar, New
Delhi 110029,
Sub:
1. Formal complaint against
Prof. K.K.Bhutani, Present Officiating Director, NIPER and Prof. P.Ramarao,
Ex-Director, NIPER (2005-2010) regarding misappropriation and diversion of 11th
Five Year Plan (2007-2012) funds to the tune of several crores.
2. Prayer for setting up
inquiry committee and appropriate action in the matter
Ref: Misappropriation of 11th Five Year Plan money allotted to
NIPER, Mohali, pertaining to project on Intellectual Property Rights (Scheme
N17), Project Outlay Rs.2.25 crores and project on new specialization in
R&D Management (Scheme N14), Project Outlay Rs.1.60 crores.
Dear Sir,
As a
responsible citizen, concerned tax-payer and keeping in view larger national
interests, I am hereby making a formal complaint to you against Prof.
K.K.Bhutani, Present Officiating Director, NIPER and Prof. P.Ramarao,
Ex-Director, NIPER (2005-2010) regarding misappropriation and large scale
diversion of 11th Five Year Plan funds and submitting prayer for
setting up an independent inquiry committee.
XXXXXXXXXXXXXXXX
I further pray for appropriate directions to
Prof. K.K.Bhutani, Officiating Director against victimizing or initiating any
disciplinary action against me under the conduct rules. To best of my
knowledge, there is nothing in the conduct rules which prevents a citizen from
acting in larger national interest. I pray for temporary relieving of
Prof.Bhutani from the Officiating Director’s post, so that a fair, impartial inquiry can be conducted without
any undue influence or fear of victimization and faculty can come forward and
speak freely.
All necessary supporting documents, evidence
and relevant information will be duly provided to the appropriate body when
required.
Sincerely,
Dr.Parikshit Bansal
C.C.
1. All BOG members 2. All NIPER faculty members 3. Visitor to NIPER 4. MOF
5. Chairman, Planning
Commission, New Delhi 6. CAG, New Delhi 7. Cabinet SecretaryDetailed chronological account of fund diversion
S.No.
|
Project Title
|
Project Code
|
Project Outlay
|
Remarks
|
1.
|
Proposal for setting up
of IPR Department at NIPER
|
N-17
|
Rs. 2.25 crores
|
No such department set up at NIPER till date. All
objectives of a project funded
in national interest, failed.
· 2006-07: Project was proposed and developed
by Dr.Parikshit Bansal, I/C Intellectual Property Rights Cell, Department of
Pharmaceutical Technology, NIPER in 2006. In 2007, Dr.Bansal presented and
defended project before planning
commission members at New Delhi and also submitted replies to subsequent
queries by members.
· 2007-09: Project got approved in 2007.
Prof.Ramarao, then Director,
NIPER concealed approval/receipt of funds from Dr.Parikshit Bansal. Rs.1.25
crores was received by NIPER over period of 3 years, without informing PI and
without any progress relating to objectives of project, taking place.
· 2009: Dr.Bansal on coming to know of
concealment of his project by Director, P.Rama Rao lodged complaint against
him with CVC in Dec.2009. No action took place, as CVO, Mr.Arun Jha, IAS was
the same person who was also involved in release of funds from the Ministry
of Chemicals and Fertilizers to NIPER.
· 2010-11: Prof.Bhutani took over.
Again diverted funds from this project. Dr.P.Bansal lodged formal complaint
with Chairman, BOG Dr.V.M.Katoch against Prof.Bhutani and Prof.Rao vide
letter dated 18-7-2011 regarding large scale misappropriation of 11th
Five Year Plan funds to tune of several crores (Ann.-1) .
· 2011-12: Action from Chairman, BOG against
Directors still awaited but meanwhile Dr.Bansal served memo and fact finding
committee set up against him at instance of Prof.Bhutani. His application for
better career prospects at NIF, Ahmedabad also damaged by Prof.Bhutani.
Major chunk of funds
diverted for purchase of a single software, Sci-finder, at an annual
recurring expense of about Rs.27 lacs every year, though same was neither
proposed nor approved under the project. How
the balance money was used is not known.
|
2.
|
Establishment of
Business Development Group at NIPER, Mohali
|
N-09
|
1.75 crores
|
No such group set up at NIPER, Mohali till date. All objectives of a project funded in national interest, failed.
·
As per note no. NIPER/DIR/OO/MTA/2011/493
dated Jan.17, 2011 from Prof. K.K.Bhutani, Officiating Director, NIPER to
Dr.Parikshit Bansal , Dr.P.Bansal was informed FOR THE FIRST TIME that
responsibility of this scheme is with him alongwith others scientists and
faculty of management. It
carried the comments “ Information on
current activities is not available.”
How much money was released/
utilized is not known.
|
3.
|
New Specialization in
Pharmaceutical Management- R&D Management
|
N-14
|
1.60
crores
|
No such specialization introduced in MBA Department till date. All objectives of a project funded in national interest, failed.
·
Main person who proposed the project i.e.
Dr.Anand Sharma, In-Charge, Department of Pharmaceutical Management was not
informed of the approval of the project at all.
·
Some new courses related to R&D management
were started in the Department in 2010, using existing department
facilities and manpower for which additional money was neither needed nor
paid out of any scheme .
·
No money released to the Department under this
project and Dr.Anand Sharma not
aware at all of this scheme.
“ In an email to Dean, Prof.
U.C.Banerjee, dated June
23, 2010 Dr. Anand Sharma wrote:
·
Total
Fund Allotted for the Scheme- Rs.1.6 crore
·
Money
spent so far on the scheme- Not known”
How much money was released/
utilized under the scheme and where it has gone is not known.
|
Total
|
5.60
|
Rs. FIVE CRORES AND SIXTY LACS ONLY
|